Current Status
Construction milestone reached — Now accepting interest from prospective residents
Construction has reached an important milestone, and the development is now nearing completion. As the project moves into its final stages, prospective residents are invited to express their interest in becoming a future tenant.
A new online platform has been created to provide information about the available homes and allow individuals and families to join the interest list for future leasing opportunities.
Homes Designed for Different Household Needs
The development will offer a variety of home sizes, including:
- 1-bedroom residences
- 2-bedroom residences
- 3-bedroom residences
Whether you are looking for a home for yourself, a couple, or a larger household, a range of floor plans will be available to meet different housing needs.
Interested in becoming a future resident? Visit the leasing platform to learn more about the available homes and join the interest list to receive updates regarding availability, leasing opportunities, and the anticipated move-in schedule. Please visit the website or send an e mail of interest.
Please note: Joining the interest list does not constitute a lease application or guarantee the availability of a unit. Additional information regarding leasing, eligibility, rents, and application procedures will be provided as units become available.
About the Project
The original, approved project entails demolishing the existing structure and building a new 73,793-square-foot multi-family apartment building. The building would be five stories and 56 feet eight inches high, with 74 units restricted to lower-income households. The application was submitted, reviewed and approved pursuant to California Senate Bill 35 (SB 35), codified in Government Code Section 65913.4.
Additional Project information
- Latest Press Release
- 8/21/2024 News Release - Portion of Marin City Affordable Housing Project Proposed for Tam Junction in Southern Marin
- Fact Sheet
- Frequently Asked Questions
- 1-12-2026 - Construction Notice Leaflet
- 1-7-2026 - News Release - Modular Building Construction Set to Begin
Project Documents
- Planning Decision
- Project Plans
- Project Plans (5.24.24)
- Project Plans (8.21.24)
- Project Plans (1.16.25)
- Revised Shoring Plan (12.31.24)
- Revised Building Permit Plans (1.15.25)
- Revised Building Permit deemed deficient and correction letter issued. (1.30.25)
- Building Permit Set Plans (3.18.25)
Recent/Upcoming Activities
- 12/6/22 – Building Permit Plans submitted.
- 5/26/23 – Building Permit issued.
- 8/13/23 – Existing structure was demolished pursuant to the building permit issued on May 24, 2023.
- 5/01/24 – News release - Revised Plan Reduces Marin City Housing Proposal
- 8/21/24 – Revised Grading Permit issued. The revised grading permit increased on-site parking from 24 spaces to 46 stalls, including two accessible to Americans with Disabilities Act (ADA) and one EV charging space.
- 8/21/24 - News Release - Portion of Marin City Affordable Housing Project Proposed for Tam Junction in Southern Marin
- 10/07/24 - Revised Grading Plan submitted on October 7, 2024
- 10/07/24 - Revised Shoring Plan submitted on October 7, 2024
- February 11, 2025, the Marin County Board of Supervisors approved an agreement for division of an affordable housing development onto two sites.
- Tuesday, March 18, 2025, the applicant resubmitted building permit plans to reduce the number of units from 74 units to 42 units. Plans are currently under review.
- 6/2/25 - Inspection Report (6.2.25)
- 6/12/25 - Inspection Report (6.12.25)
- 7/3/25 - Inspection Report (7.3.25)
- 7/17/25 - Inspection Report (7/18/25)
- 7/25/25 - Inspection Report (7/25/25)
- 8/5/25 - Inspection Report (8/5/25)
- 8/11/25 - Inspection Report (8/11/25)
- 8/25/25 - Inspection Report (8/25/25)
- 9/2/25 - Inspection Report (9/2/25)
- 9/5/25 - Inspection Report (9/5/25)
- Revised Construction Update (Leaflet) for October 1 (previously September 26) and fall 2025
- 9/22/25 - Inspection Report (9/22/25)
- 9/29/25 - Inspection Report (9/29/25)
- 10/03/25 - Inspection Report (10/03/25)
- 10/07/25 - Construction Update (Leaflet 10/7/25)
- 10/13/25 - Inspection Report (10/10/25)
- 10/17/25 - Inspection Report (10/17/25)
- 10/23/25 - Construction Update (Leaflet 10/31/25)
- 10/23/25 - Inspection Report (10/23/25)
- 10/29/25 - Construction Update (Leaflet 11/03/25)
- 10/31/25 - Inspection Report (10/31/25)
- 11/10/25 - Inspection Report (11/07/25)
- 11/10/25 - Construction Update (Leaflet 11/05/25)
- 11/26/25 - Construction Update (Leaflet 11/26/25)
- 12/2/25 - Inspection Report (11/20/25)
- 12/05/25 - Inspection Report (12/05/25)
- 09/24/26 - Inspection Report (09/24/26)
About SB 35
SB 35 is a 2017 state law designed to streamline housing development in counties that have not met their state-mandated housing goals, particularly for affordable housing. It allows projects like 825 Drake Avenue to bypass certain local approval processes, including the normally required environmental review, public hearings, and discretionary reviews. This means it can move forward through the review process and restricts a local government’s ability to reject a project that has minimum affordable housing guarantees.
- Frequently Asked Questions for Senate Bill 35 Streamlined Multifamily Review Process