The Marin County Department of Public Works is proposing to perform pavement rehabilitation and build approximately 500 linear feet of new sidewalk along Lomita Drive, closing several gaps in the pedestrian network. As part of the Project, the County will remove vegetation, construct sidewalks, new curbs and gutters, pedestrian curb ramp access, driveway approaches, concrete driveway conforms, storm drain maintenance hole cover(s), drop inlet turning structures, storm drain infrastructure, and will complete grinding and paving, or micro-surfacing, of the full 2,900 linear feet of pavement. The County will also adjust utilities and pavement markings as needed. Some excavation and some infill will be necessary to correct the topography of the road for improved surface drainage. Excavations for road grading will be less than 18 inches below ground surface. The County will also adjust utilities and pavement markings as needed.

Subsurface work and excavation/trenching will be required for stormwater infrastructure. New or reconfigured subsurface storm drains would be installed at the western end of the Project near Edna Maguire Elementary School, along the north and the south side of Lomita Drive within the Right-of-Way (ROW) adjacent to the southern parcel line of the school, and on the north side of Lomita Drive within the ROW between Shell Road and the eastern end of the Project site. These new or replaced storm drains would connect into the existing storm drain system along Lomita Drive. Trenching and other ground-disturbing work associated with the storm drain system improvements would have a maximum depth of 10 feet below ground surface. 

Review type

Mitigated Negative Declarations (MND)

Estado

Active

Ubicación

Location

The Project site is located along Lomita Drive, between its intersection of Somerset Lane and east to the Hill Preserve, adjacent to U.S. Highway 101, in unincorporated Marin County adjacent to the City of Mill Valley and in the City of Mill Valley. 

Applicant

Rachel Calvert , Senior Civil Engineer/PMP Manager

Notice of Availability

Notice of Availability

The Marin County Department of Public Works has completed a Draft Initial Study/Mitigated Negative Declaration for the Lomita Drive Road Rehabilitation Project. The Draft Initial Study/Mitigated Negative Declaration is linked below in the "Environmental Review Documents" section near the bottom of this webpage. The 30-day public comment period on the adequacy of the Draft Initial Study/Mitigated Negative Declaration began on Monday, June 30, 2025 and ended on Wednesday, July 30, 2025. 

A Response to Comments document is being prepared to address the written comments received during the public comment period. The Response to Comments will be uploaded to this project webpage when completed. 

Public Notice

Public Notice

Notice of Availability - Draft Initial Study/Mitigated Negative Declaration

Environmental Review Documents

The documents in this list may not work with all assistive technology and are being remediated. For alternative formats, please email Tammy Taylor or phone 415-473-7873. To use the California relay service, dial 711.

  • Lomita Drive - Draft IS/MND (18.02 MB) — The Draft Initial Study/Mitigated Negative Declaration (IS/MND) for the Lomita Drive Road Rehabilitation Project.